Currently, reinforcement works are carried out during the day, and concreting works at night, due to the lower temperature. Three kilometers of track, the western turnout head and about 60% of the storage plate have already been completed. The eastern turnout head, track number 601, along the E-20 line, and the rest of the transfer plate remained to be built.