Work is underway on the expansion of the CLIP Intermodal Terminal
10 August 2021
Currently, reinforcement works are carried out during the day, and concreting works at night, due to the lower temperature. Three kilometers of track, the western turnout head and about 60% of the storage plate have already been completed. The eastern turnout head, track number 601, along the E-20 line, and the rest of the transfer plate remained to be built.